For a road work, a contractor was given a deadline to complete the work in 25 days. Hence, he employed a certain number of workers to accomplish the job. But from the very first day 9 workers were absent and the remaining workers could finish the work in 40 days. What number of workers did the contractor hired in the beginning? | |
A. | 20 [Wrong Answer] |
B. | 30 [Wrong Answer] |
C. | 24 [Correct Answer] |
D. | 16 [Wrong Answer] |