A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more Âafter 35 days and completes the work in stipulated time. If he had not Âengaged Âthe additional men, how many days Âbehind schedule would it be finished? | |
A. | 3 [Wrong Answer] |
B. | 5 [Correct Answer] |
C. | 6 [Wrong Answer] |
D. | 9 [Wrong Answer] |