A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work? | |
A. | 13 [Correct Answer] |
B. | 11 [Wrong Answer] |
C. | 12 [Wrong Answer] |
D. | 15 [Wrong Answer] |