The reduction in project time normally results in | |
A. | decreasing the direct cost and increasing indirect cost [Wrong Answer] |
B. | increasing the direct cost and decreasing the indirect cost [Correct Answer] |
C. | increasing the direct cost and indirect cost both [Wrong Answer] |
D. | decreasing the direct cost and indirect cost both [Wrong Answer] |