For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is | |
A. | 8 days [Wrong Answer] |
B. | 9 days [Correct Answer] |
C. | 10 days [Wrong Answer] |
D. | 15 days [Wrong Answer] |