If 28 men can finish a work in 15 days, 21 men can finish the same work in | |
A. | 24 days [Wrong Answer] |
B. | 14 days [Wrong Answer] |
C. | 15 days [Wrong Answer] |
D. | 20 days [Correct Answer] |