A can lay a railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in | |
A. | 4 [Wrong Answer] |
B. | 9.6 [Correct Answer] |
C. | 9 [Wrong Answer] |
D. | 10 [Wrong Answer] |