Users Also Read
Read MCQ's/Objective questions
MCQ's Search Engine
Airport Engineering
Applied Mechanics & Graphic Statics
Building Materials and Construction
Concrete Technology (R.C.C.)
Dock and Harbor Engineering
Environmental Engineering
Estimation Costing, Quantity Surveying
Fluid Mechanics/Hydraulic Engineering
Highways Engineering
Railway Engineering
Sanitary Engineering
Soil Mechanics and Foundation Engg
Steel Structures & it's Design
Strength of Materials
Surveying
Theory/Design of Structures Analysis
Tunnel Engineering
Water Res. Engg, Irrigation, Hydrology
Air Pollution
Home⇒ Engineering⇒
Construction planning and manag pert
1-Dont try to cram or spend more time here just read it fast and cover syllabus then practice MCQ's cheptor of same topic to check your progress. . |
2-Wrong options are also given but dont concentrate there, Right answer is in bold format. |
Q21 ⇒ Which of the following is not a PERT event ? class is being attended [other wrong options] [Discuss in forum] ![]() ![]() site investigation started sessional work completed bus starts from Jaipur |
Q22 ⇒ Which of the following is an activity ? Excavation for foundation [other wrong options] [Discuss in forum] ![]() ![]() Concrete cured Walls plastered All of the above |
Q23 ⇒ In PERT analysis, the time estimates of activities and probability of their occurrence follow Beta - distribution curve [other wrong options] [Discuss in forum] ![]() ![]() normal distribution curve Poisson's distribution curve none of the above |
Q24 ⇒ In PERT analysis the duration of the activities
is taken as Expected mean time [other wrong options] [Discuss in forum] ![]() ![]() Optimistic time Pessimistic time Most likely time |
Q25 ⇒ The area under the Beta - distribution curve is divided into two equal parts by expected time [other wrong options] [Discuss in forum] ![]() ![]() most likely time optimistic time pessimistic time |
Q26 ⇒ According to Fulkerson's rule, what are the correct event numbers corresponding to events A, B, C, D,E, F and G of the network shown in Fig. ? 1, 3,2,4, 5,6 and 7 respectively [other wrong options] [Discuss in forum] ![]() ![]() 1, 2,3, 4, 5, 6 and 7 respectively 1,2, 3, 5, 6,4 and 7 respectively 1, 3,2, 5, 6,4 and 7 respectively |
Q27 ⇒ With reference to the network shown in Fig. , which statement is incorrect ? Event 7 can occur after event 4. [other wrong options] [Discuss in forum] ![]() ![]() Events 3 and 4 occur after event 2. Event 7 precedes event 6. Event 5 follows event 3. |
Q28 ⇒ In the network shown in Fig., the concurrent and preceding activities corresponding to activity 2-4 are respectively 2-3 and 1-2 [other wrong options] [Discuss in forum] ![]() ![]() 1-2 and 4-7 2-3 and 4-7 1-2 and 3-6 |
Q29 ⇒ Which of the following does not represent an activity? site located [other wrong options] [Discuss in forum] ![]() ![]() foundation is being dug the office area is being cleaned the invitations are being sent |
Q30 ⇒ Earliest finish of an activity is always less than or equal to earliest event time of the following node [other wrong options] [Discuss in forum] ![]() ![]() greater than earliest event time of the following node less than earliest event time of the following node greater than or equal to earliest event time of the following node |
Q31 ⇒ Select the incorrect statement. none of the above [other wrong options] [Discuss in forum] ![]() ![]() Earliest start of an activity is the early event time of the node it leaves. Latest finish of an activity is the late event time of the node it enters. Latest start of an activity is its latest finish minus its duration. |
Q32 ⇒ In the network shown in Fig. the earliest start time of activity 5-6 is (the number on the arrow shows duration of the activity) 9 [other wrong options] [Discuss in forum] ![]() ![]() 7 8 5 |
Q33 ⇒ Latest start of an activity is always greater than or equal to latest event time of preceding node [other wrong options] [Discuss in forum] ![]() ![]() less than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node |
Q34 ⇒ In the network shown in Fig. the latest start time of an activity 4-5 is 4 [other wrong options] [Discuss in forum] ![]() ![]() 2 8 7 |
Q35 ⇒ In the network shown in Fig. , the activity 6-8 can be started only when both activities 2—3 and 4—6 are completed [other wrong options] [Discuss in forum] ![]() ![]() activity 4—6 is completed activity 3 - 5 is completed activity 2—3 is completed |
Q36 ⇒ If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same [other wrong options] [Discuss in forum] ![]() ![]() expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A none of the above |
Q37 ⇒ If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 [other wrong options] [Discuss in forum] ![]() ![]() 3.5 and 5/6 5 and 25/36 4 and 5/6 |
Q38 ⇒ Select the incorrect statement. Start float and finish float need not be equal. [other wrong options] [Discuss in forum] ![]() ![]() Start float and finish float are always equal. Total float can be either start float or finish float. Start float and finish float are the differences between activity times and not event times. |
Q39 ⇒ Free float is mainly used to identify the activities, which can be delayed without affecting the total float of succeeding activity [other wrong options] [Discuss in forum] ![]() ![]() identify the activities which can be delayed without affecting the total float of preceding activity establish priorities identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities |
Q40 ⇒ Whenever an activity has zero total float, then free float and independent float both must be zero [other wrong options] [Discuss in forum] ![]() ![]() free float of the activity must be zero but independent float need not be zero independent float must be zero but free float need not be zero free float and independent float both need not be zero |