Load factor of a power station is defined as | |
A. | maximum demand/average load [Wrong Answer] |
B. | average load X maximum demand [Wrong Answer] |
C. | average load/maximum demand [Correct Answer] |
D. | (average load X maximum demand)1/2 [Wrong Answer] |
![]() |