Indirect cost of the project | |
A. | Decrease with duration [Wrong Answer] |
B. | Decrease upto optimum duration and then increase with duration [Wrong Answer] |
C. | Increase with duration [Correct Answer] |
D. | All of the above [Wrong Answer] |