In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having | |
A. | longest duration [Wrong Answer] |
B. | highest cost slope [Wrong Answer] |
C. | least cost slope [Correct Answer] |
D. | shortest duration [Wrong Answer] |