In crash programe for a project | |
A. | both direct and indirect costs, increase [Wrong Answer] |
B. | indirect costs increase and direct costs decrease [Wrong Answer] |
C. | direct costs increase and indirect costs decrease [Correct Answer] |
D. | cost is no criterion [Wrong Answer] |
E. | none of the above. [Wrong Answer] |