In analysis of rate the quantity of dry mortar for 10 cubic metre brick work is taken as | |
A. | 10 m3 [Wrong Answer] |
B. | 3 m3 [Correct Answer] |
C. | 0.3 m3 [Wrong Answer] |
D. | 1 m3 [Wrong Answer] |