If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is | |
A. | 4 days [Wrong Answer] |
B. | 6 days [Wrong Answer] |
C. | 10 days [Wrong Answer] |
D. | 16 days [Correct Answer] |