If P, Y and Z are the weights of cement, fine aggregates and coarse aggregates respetively and W/C is the water cement ratio, the minimum quantity of water to be added to first batch, is obtained by the equation. | |
A. | 0.1P + 0.3Y + 0.1Z = W/C x P [Wrong Answer] |
B. | 0.3P + 0.1Y + 0.01Z = W/C x P [Correct Answer] |
C. | 0.4P + 0.2Y + 0.01Z = W/C x P [Wrong Answer] |
D. | 0.5P + 0.3Y + 0.01Z = W/C x P [Wrong Answer] |