For strengthening a 50 m long and 5 m high straight compound wall built in brick work, which one of the following would be most suitable? | |
A. | providing buttresses at certain intervals [Correct Answer] |
B. | providing a deeper foundation [Wrong Answer] |
C. | using a richer mortar [Wrong Answer] |
D. | using stronger bricks [Wrong Answer] |