A works thrice as much as B. If A takes 60 days less than B to do a work then find the number of days it would take to complete the work if both work together? | |
A. | 20 days [Wrong Answer] |
B. | 22.5 days [Correct Answer] |
C. | 25 days [Wrong Answer] |
D. | 30 days [Wrong Answer] |