36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work? | |
A. | 12 [Wrong Answer] |
B. | 18 [Wrong Answer] |
C. | 22 [Wrong Answer] |
D. | 24 [Correct Answer] |