Efficiency of Amit and Anish are in the ratio 5:8. If Anish takes 51 days less than Amit to complete the work, find the time taken by Amit to complete the work. | |
A. | 85 days [Wrong Answer] |
B. | 126 days [Wrong Answer] |
C. | 118 days [Wrong Answer] |
D. | 136 days [Correct Answer] |