An optimum project schedule implies | |
A. | optimum utilization of men, machines and materials [Wrong Answer] |
B. | lowest possible cost and shortest possible time for project [Correct Answer] |
C. | timely execution of project [Wrong Answer] |
D. | to produce best results under given constraints [Wrong Answer] |
E. | realistic execution time, minimum cost and maximum profits. [Wrong Answer] |