A is thrice as good a work man as B and takes 10 days less to do a piece of work than B takes. B can do the work in : | |
A. | 15 days [Correct Answer] |
B. | 14 days [Wrong Answer] |
C. | 16 days [Wrong Answer] |
D. | 30 days [Wrong Answer] |