A channel is said to be of most economical cross-section, if. | |
A. | it gives maximum discharge for a given cross-sectional area and bed slope [Wrong Answer] |
B. | it has minimum wetted perimeter [Wrong Answer] |
C. | it involves lesser excavation for the designed amount of discharge [Wrong Answer] |
D. | all of the above [Correct Answer] |